Abbey ground toilets

Project Overview: 

MBM was instructed to deliver drainage repairs to the new toilets.

Client Requirements:

The client required extensive drainage repairs, further complicated by an archeological dig required. 

Scope of Works: 

  • Excavate to 2m deep, by hand due to archeological dig.

  • Installation of protection measures.

  • Undertake pipe renewal.

  • Backfill and make good.

Results and Outcome:

The project was completed to a high standard. All work was carried out on time and within budget, causing minimal disruption.

Previous
Previous

Montpellier Toilets

Next
Next

RAF Benson